Expansion of Renewable Energy Projects
The Serra do Assuruá Wind Complex reached 100% physical progress with 88% commercially operating. A photovoltaic complex achieved 96% fiscal progress with 24% of the plants under commercial operation. These projects are expected to be fully operational by the end of the third quarter.
Significant Debenture Issuance
ENGIE Brasil concluded its 15th debenture issuance totaling BRL 2.2 billion, classified as a green debenture, showing strong capital acquisition capabilities.
Transmission Project Progress
The Asa Branca project is on track, with the first area representing 1/3 of the IP set to start operating early this year. The Grauna project is also progressing, with important synergies identified.
Client Base Growth
The company experienced an increase of almost 22% in the number of clients and a 15% increase in consuming units compared to the second quarter of '24.
Improved ESG Performance
ENGIE Brasil maintained low emissions intensity, significantly below NIS reference, and improved safety and diversity indicators.