Strong Liquidity Position
Algoma Steel Group Inc. maintained a strong balance sheet with over $267 million in cash at the end of the quarter and total liquidity of $630 million.
Progress on Electric Arc Furnace Project
The Electric Arc Furnace (EAF) project is on schedule with first steel production expected in April 2025. The project remains on budget with cumulative investment at $740 million.
Plate Shipments Increase
Plate shipments for Q4 2024 reached approximately 82,000 tons, up from 73,000 tons in Q3 2024, with plans to increase production further in Q1 2025.
Expected Cost Reduction from EAF Transition
Transitioning to EAF steelmaking is expected to strengthen Algoma's cost structure, with the full conversion cost expected to be $200 to $220 USD per ton.
Insurance Payout Expected
Algoma expects to receive an insurance payout related to a previous outage, with $20 to $25 million anticipated in the next month and the balance by year-end.