Shimmick comments on Legacy Projects and backlog begun with AECOM

As part of the AECOM Sale Transactions, assumed the Legacy Projects and backlog that were started under AECOM. Legacy Projects revenue was $(2)M , a decline of $44M as the company works to complete these projects. As part of a settlement of a claim on a large Legacy Loss Project, we made a non-cash adjustment to revenue of $23M to reflect the settlement amount. See Recent Developments for additional details. Gross margin was $(34)M a decrease of $32M as compared to the three months ended June 30, 2023, primarily as a result of the $30 million impact of the settlement, projects winding down and additional cost overruns on a subset of these projects that have experienced significant cost overruns due to the COVID pandemic, design issues, legal costs and other factors.