Tlou Energy Ltd. (AU:TOU) has released an update.
Tlou Energy Ltd. has made significant strides in its Lesedi project, successfully completing the construction of a 66kV transmission line and making progress on a substation, which is now 50% complete, to connect its power generators to Botswana’s national grid. The company continues to produce gas at Lesedi 4 and Lesedi 6 production pods, with preparations for further drilling underway. These developments mark a substantial step forward in Botswana’s gas to power sector and Tlou’s proposed 10MW gas-to-power project.