Endeavour Silver (TSE:EDR) has released an update.
Endeavour Silver reports that their Terronera Project in Jalisco, Mexico, has achieved 77% completion in surface construction with the overall project 64.5% complete, maintaining its schedule for a Q4 2024 commissioning. The company has made significant advances in mine development and construction, with critical structural components near completion and underground operations progressing as planned. Endeavour emphasizes its commitment to safety, community relations, and environmental impact assessment, which remains on track despite a minor delay.