B2Gold (TSE:BTO) has released an update.
Claim 30% Off TipRanks
- Unlock hedge fund-level data and powerful investing tools for smarter, sharper decisions
- Discover top-performing stock ideas and upgrade to a portfolio of market leaders with Smart Investor Picks
B2Gold Corp. has successfully completed its planned construction for 2024 at the Goose Project in Nunavut, staying on schedule for initial gold production in Q2 2025, with an expected annual output of 310,000 ounces over the first five years. However, the construction and development costs have risen to C$1,540 million, a 23% hike largely due to a delay in production and the acceleration of capital investments aimed at enhancing project reliability.